A stone manufacturer cut electricity use about 30% with no new machinery

Case study · Manufacturing · Lean operations

A stone manufacturer ran three facilities with no standard work and no quality gate. Embedded for 12 to 16 weeks, Armstrat cut electricity use about 30% and net operating cost 5 to 7%.

Client
A natural stone products manufacturer and exporter running three specialized facilities
Engagement
Operations transformation across three sites, delivered in 12 to 16 weeks
Result
Electricity use down about 30%, water use down 25%, net operating cost down 5 to 7% after a 30% payroll increase
How we worked
Embedded on the floor at every facility, with production at full volume and the work judged against measured cost, utility and output

Published . Client name withheld.

30%Approximate reduction in electricity use, with no new machinery bought

The situation

The client manufactures and exports natural stone products, from bespoke architectural pieces such as bathtubs and fireplaces to small items like chessboards and wine cups, across three specialized facilities. The business was profitable in spite of its operations rather than because of them. A single general operations manager rotated between the three sites while also carrying logistics and supply chain.

Skilled day-wage craftsmen worked each order by their own method, with no standard work and no written instructions. There was no quality assurance function and no formal way to turn customer requirements into floor instructions, so orders were regularly made to the wrong specification and remade at double cost. Machines ran idle between block loads, water and electricity use went uncontrolled, and process waste piled up with no owner.

What made it hard

  • No capital budget. Every gain had to come from method, sequence, layout and utilization, not new equipment.
  • Three facilities specialized in genuinely different processes, so no single template fit, and layout or scheduling changes at one site carried through to the others.
  • Production ran at full volume throughout, with no shutdown window.
  • Critical process knowledge sat undocumented with long-tenured staff, and the incumbent operations manager had to be replaced despite internal resistance.
  • Fixing accountability meant raising payroll 30% inside a cost reduction mandate, so the offset had to be proven, not assumed.
A wall of natural stone blocks laid by hand.

How we worked

Armstrat worked inside the business, on the floor at all three facilities, while production continued at full volume. The engagement was scoped against measurable results in utility use, operating cost and output quality, and the 30% payroll increase was approved only once measured utility and throughput savings covered it. We stayed through implementation rather than handing over a plan.

  1. 01

    Audit every step on the floor

    We ran a gemba-based audit at each facility, measuring every process step and output against product-level manufacturing requirements, industry standard and unit cost rather than historical practice. We mapped the eight wastes, concentrating on defects and rework, waiting, transport between facilities, extra processing and unused talent.

  2. 02

    Rebuild crews around engineering method

    An industrial engineer went onto the floor to set standard work and drive method improvement. Crews moved from one lead laborer supervising 10 to one industrial engineer with 4 to 5 laborers, each on a salaried contract with individual metrics for volume, client, timing and quality.

  3. 03

    Cut utility use without CapEx

    With no capital budget, every gain had to come from method. We treated machine changeover between block loads as a SMED problem, sequencing loads to keep cutting continuous. Labor breaks were rescheduled to protect machine uptime, and water controls went in across cutting and finishing.

  4. 04

    Turn waste into space and cash

    We redesigned facility layouts to cut material movement and worker motion, and applied 5S with named ownership for waste removal. A recycling offtake contract turned accumulated process waste from a disposal problem into a cash inflow that helped fund an in-house packaging capability.

  5. 05

    Install quality and accountable leadership

    A new operations manager with supply chain and process improvement experience replaced the incumbent through a structured handover. Dedicated QA managers and a formal pre-dispatch inspection gate moved specification checks in-house, before the customer. Discretionary facility spending, including hosted meetings, came under control.

The results

Measured against the outcomes agreed at the start.

30%
  • Electricity use down about 30%, from eliminating idle machine running and improving cutting continuity.
  • Water consumption down 25%, measured at just over 24% before rounding.
  • Production and operations cost down about 15%, excluding payroll.
  • Net operating cost down 5 to 7% after fully absorbing a 30% payroll increase from professional hires and salaried contracts.
  • Crew size down about 50%, from 11 to 5 or 6 people per crew, with output and quality improving rather than falling.
  • An estimated 4 to 6 percentage points of the 10 point EBITDA margin expansion delivered across the wider engagement, in 12 to 16 weeks with no production shutdown and no new machinery.

What leaders can take from it

  • Adding cost to reduce cost works when the arithmetic is proven first. A 30% payroll increase was defensible only because measured utility and throughput savings already covered it. Judge the change on total cost and output, never on headcount.
  • Skilled craft is not the same as efficient process. Capable craftsmen without standard work produce good pieces and bad economics. In bespoke work the most expensive defect is a specification error, because a piece cut wrong has no salvage value.
  • Waste with no assigned owner is a design problem, not a discipline problem. 5S works because it assigns the name, not the broom. Once someone owns it, waste becomes reclaimed floor space and cash.

Questions about this work

How can a manufacturer cut operating costs without buying new equipment?

Change method, sequence, layout and utilization before spending on machinery. At a natural stone manufacturer with no capital budget, Armstrat audited every process step on the floor, sequenced block loads to keep cutting continuous, controlled water use and redesigned layouts. Electricity use fell about 30%, water use 25% and production and operations cost about 15% excluding payroll, with no production shutdown.

Can raising payroll actually lower total operating cost in a factory?

Yes, if the savings are measured before the payroll decision is made. In an Armstrat engagement, a natural stone manufacturer moved day-wage laborers to salaried contracts with individual metrics and rebuilt crews around industrial engineers, raising payroll 30%. Because utility and throughput savings were proven first, net operating cost still fell 5 to 7%, and output and quality improved.